Programme status key
Description |
Status |
SCHEME PROGRAMMED TO BE DELIVERED - ( Approximate duration and START month indicated ) |
Scheduled |
SCHEME UNDERWAY - WORK IN PROGRESS - (Traffic Management as required, during works) |
In progress |
WORKS ONSITE SUBSTANTIALLY COMPLETE. ( Road Markings and White Lining - Weather permitting ) |
Complete |
Last updated - 25th October 2024
Oban and Lorn
Carry over budget from 2023/24
Oban and Lorn carry over from 2023/24
Location |
Treatment type |
Duration - days |
Start month |
Status |
A816 Blaran widening PH4 ( No STTS award 2024) |
Reconstruction c/o |
25 |
Jul-24 |
Complete |
Surface dressing and pre-surface dressing
Oban and Lorn surface dressing and pre-surface dressing
Location |
Treatment type |
Duration - days |
Start month |
Status |
2024 laying operations - North Shian - C27 Pt Appin |
SD 2024 |
5 |
Jul-24 |
Complete |
2024 laying operations - North Shian - U42/U44 - Inverfolla |
SD 2024 |
4 |
Jul-24 |
Complete |
U25 Musdale Road |
Pre-SD 2025 |
20 |
Feb-25 |
Scheduled |
U14 Scammadale Road |
Pre-SD 2025 |
15 |
Feb-25 |
Scheduled |
Bituminous surfacing etc.
Oban and Lorn bituminous surfacing
Location |
Treatment type |
Duration - days |
Start month |
Status |
C29 - Kilmelford-Drissaig - Lochavich |
Overlay |
10 |
Apr-24 |
Complete |
U48 Shore Street - Oban |
Inlay |
5 |
Oct-24 |
Complete |
U17 McCaig Road - Oban |
Inlay |
10 |
Jul-24 |
Complete |
U 51 Dunuran Road - Oban |
Inlay |
2 |
Jun-24 |
Complete |
U 45 High St - Oban |
inlay |
5 |
Jun-24 |
Complete |
B845 - Glen Salach ( Blarcreen & Summit ) |
Overlays |
5 |
Nov-24 |
Scheduled |
A819 Cladich PH 3 - ( O/lay Ph 1&2 ) |
Overlays |
20 |
Nov-24 |
Scheduled |
U58 Lower Gylen to Little Horse Shoe Bay KERRERA |
Overlay |
5 |
Sep-24 |
Complete |
U 16 Laurel Road - Oban |
Inlay |
5 |
May-24 |
Complete |
U22 Achavaich Road |
Major Maintenance |
5 |
May-24 |
Complete |
C32 Glencruitten Road |
Overlay |
5 |
May-24 |
Complete |
U28 - Achnacloich - Connel |
Overlay |
3 |
May-24 |
Complete |
U32 Craig Road - Dalmally |
Overlay |
3 |
May-24 |
Complete |
U 76 Shore Road - Connel |
Overlay |
3 |
May-24 |
Complete |
U 135 Pulpit Drive -Oban |
Inlay |
5 |
Jun-24 |
Complete |
Mull and the Isles
Carry over budget from 2023/24
Mull and the Isles carry over from 2023/24
Location |
Treatment type |
Duation - days |
Start month |
Status |
Isle of Coll - B8027 Sorisdale Road (ferry delays 2023) |
Overlay |
15 |
Apr-24 |
Complete |
Surface dressing preparation
Mull and the Isles surface dressing preparation
Location |
Treatment type |
Duration - days |
Start month |
Status |
C46 Glen Bellart / Glen Aros |
Pre-SD 2025 |
5 |
Sept-24 |
Complete |
Bituminous surfacing etc.
Mull and the Isles bituminous surfacing
Location |
Treatment type |
Duration - days |
Start month |
Status |
B8073 Calgary area - Mull |
Overlay |
4 |
Aug-24 |
Complete |
B8073 Tobermory - Dervaig |
Overlay |
4 |
Aug-24 |
Complete |
B 8073 Balligowan |
Overlay |
4 |
Aug-24 |
Complete
|
B 8073 Killichronan |
Overlay |
4 |
Aug-24 |
Complete
|
B 8073 Killiemore |
Overlay |
4 |
Aug-24 |
Complete
|
U82 Leiter Rd |
Overlay |
1 |
Sep-24 |
Complete |
C 54 Loch Buie Rd |
Overlay |
3 |
Sep-24 |
Complete |
U16 Croggan Road |
Overlay |
3 |
Feb-25 |
Scheduled |
U14 Grasspoint |
Overlay |
3 |
Feb-25 |
Scheduled |
C 54 Lay-by improvement works |
Overlay |
20 |
Jun-24 |
Complete |
B8035 Gruline North - Mull |
Overlay |
3 |
Sep-24 |
Complete |
B8035 Gruline South - Mull |
Overlay |
3 |
Sep-24 |
Complete |
U80 Java Road |
Inlay |
1 |
Feb-25 |
Scheduled |
A848 Additional Passing Places - Salen - Gulan Dubh |
construction |
20 |
Feb-25 |
Scheduled |
B8065 Tiree |
Overlay |
10 |
Apr-24 |
Complete |