Programme status key
Description |
Status |
SCHEME PROGRAMMED TO BE DELIVERED - ( Approximate duration and START month indicated ) |
Scheduled |
SCHEME UNDERWAY - WORK IN PROGRESS - (Traffic Management as required, during works) |
In progress |
WORKS ONSITE SUBSTANTIALLY COMPLETE. ( Road Markings and White Lining - Weather permitting ) |
Complete |
Last updated - 25th October 2024
Cowal
Carry over budget from 2023/24
Cowal carry over from 2023/24
Location |
Treatment type |
Duration - days |
Start Month |
Status |
A8003 Tighnabruaich Ph 7 (no STTS award 2024 ) |
Reconstruction c/o |
30 |
Sept-24 |
Scheduled |
Surface dressing and pre-surface dressing
Cowal surface dressing and pre-surface dressing
Location |
Treatment type |
Duration - days |
Start month |
Status |
A815 Var location below PSD |
Pre-SD 2024 |
15 |
Apr-24 |
Complete |
A815 Coylet - Inverchapel |
Laying 2024 |
2 |
Jul-24 |
Complete |
A815 Alexandar Parade - Marine P- Pt Riddle |
Laying 2024 |
1 |
Jul-24 |
Complete |
A815 Braemar Cottage - Kelani Toward |
Laying 2024 |
2 |
Jul-24 |
Complete |
U27 Millhouse / U19 Couston |
Pre-SD 2025 |
25 |
Feb-25 |
Scheduled |
Bituminous surfacing etc.
Cowal bituminous surfacing
Location |
Treatement type |
Duration - days |
Start month |
Status |
C7 - from B8000 to Tank Landing - Kames |
Overlay |
13 |
Jul-24 |
Complete |
A886 Dunans House Northwards (2 sites) |
Overlay |
15 |
Jun-24 |
Complete |
A886 North of Communications Mast ( Leanach) |
Overlay |
15 |
Jun-24 |
Complete |
A886 Ardachuple cutting - Colintaive ( 2 sites) |
Overlay |
15 |
May-24 |
Complete |
A886 Baycrofts to A815 junction - Strachur |
Inlay |
9 |
Aug-24 |
Complete |
B839 / B828 Passing Place improvements |
construction |
35 |
Oct-25 |
Scheduled |
B8000 Largiemore ( C11 Junction) |
Overlay |
9 |
Jul-24 |
Complete |
Bute
Surface dressing preparation
Bute surface dressing preparation
Location |
Treatment type |
Duration - days |
Start month |
Status |
C1 Bruchag Road |
2025 Pre-SD |
15 |
Oct-24 |
Complete |
Bituminous surfacing etc.
Bute bituminous surfacing
Location |
Treatment type |
Duration - days |
Start month |
Status |
A844 East Princess St & Battery place to Glenburn rd |
Inlay |
12 |
Oct-24 |
Complete |
A844 Stewarthall to Milton Farm |
o/lay |
7 |
May-24 |
Complete |
A844 Meikle Kilmory |
o/lay |
6 |
May-24 |
Complete |
U58 Serpentine Rd - to B881 Bishop St |
Inlay |
5 |
Oct-24 |
Complete |
U39 /U69 Gowanfield Place to St Brides Rd |
Inlay |
7 |
Oct-24 |
Complete |
Ascog Roslin to High Bogany Farm |
o/lay |
6 |
May-24 |
Complete |
Glenburn Rd |
inlay |
5 |
Oct-24 |
Complete |