29th November - The bridge arrived on site on 28 November and we carried out the additional works required, such as completing approach ramps and surfacing works.
We remained on track to safely re-open the route on Friday 1 December subject to no additional issues.
This is a map which shows the new alignment of the road at Balliemore Bridge, where the new temporary bridge will go slightly upstream of the existing bridge. The old bridge will be demolished and a permanent replacement progressed for April 2024.
This image shows works ongoing on the new road connections to the new bridge, upstream of the original bridge -
This image shows the temporary diversion road being constructed through field to north west of the Balliemore Bridge -