¾ÅÐãÖ±²¥

A816 at Ardfern landslip - gallery

Following the landslip on the A816 near Ardfern on 7th October, work is progressing to clear the road and progress the emergency road.

We received 240 tonnes of material on site on 13 December to enable us to start surfacing the emergency bypass. The new bypass opened for use on 16 December 2023.

Image
A816 landslip at Ardfern - 13th December - tarmac being laid

 

Image
A816 landslip at Ardfern - 13th December - workers laying tarmac on the bypass road

 

Image
A816 landslip at Ardfern - 13th December - progress is being laying tarmac on the bypass road

6th December - "It was a pleasure coming across this morning." This was the comment from one of the passengers currently using the boat to commute from Ardfern to Crinan while the A816 is closed.

Image
Boat travel from Ardfern

4th December - This is an image of the new road from the Kilmartin end looking north with the new road going through the trees - 

Image
A816 landslip at Ardfern - 4th December - new road from the Kilmartin end

4th December - This is an image of the new road looking south, back towards the A816 main road - 

Image
A816 landslip at Ardfern - 4th December - new road from the south

29th November - Emergency route on track to open 16 December, subject to weather or other unforeseen circumstances.

Image
A816 landslip at Ardfern - 29th November - work progressing on the emergency road

27 November 2023 - The southern half of the emergency route (forestry route) has been excavated down to formation level. Geotextile grid has been laid across the formation and the stone subbase has been imported.

Image
A816 landslip at Ardfern - 27th November - excavation of the forestry route

 

Image
A816 landslip at Ardfern - 27th November - laying the geotextile grid

27 November 2023 - We are continuing to remove spoil and boulders that came down as part of the debris flow. We have removed 15,000 tonnes of debris to date.

Image
A816 landslip at Ardfern - 27th November - clearing soil and boulders

A816 timescales – here’s a map of what we’re working to deliver. We had hoped to re-open the A816 route mid to end November. The unsafe state of the hillside unfortunately rules that out. So we are progressing the diversion route, for opening mid-December subject to any new issues, while we continue to clear and stabilise the A816.

Image
A816 landslip - map of proposed works

4th November - This is an example of the boulders that we’re working to bring down safely from the hillside as we continue clearance operations at Ardfern. This one is estimated to be about 20 tonnes. 

Image
Boulders at Ardfern landslip 4th November 2023

4th November - This is what remains of a 220-tonne boulder that our teams had to break up at the site of the landslip at Ardfern.

Image
Remains of a boulder at Ardfern landslip - 4th November 2023

 

4th November - work continues to clear 6,000 of debris from the road

Image
Ardfern landslip - work continues to clear 6,000 of debris from the road

 

Image
Ardfern landslip - work continues to clear 6,000 of debris from the road - clearing mud and boulders

 

31st October - images of our teams working on the clean up after the landslip

Image
Roads team working on clearing the road after the Ardfern landslip

 

Image
Roads team using machinery to work on clearing the road after the Ardfern landslip
Did you find what you were looking for?

Why wasn't this information helpful

Limit to 250 characters.